Centrifuge Application Guide

Industrial Centrifuges for Salt Crystallization and Dewatering

Salt centrifuge selection depends on crystal distribution, mother liquor, feed solids, temperature, washing, corrosion and breakage limits. The salt name and hourly requirement are not enough.

Blue and stainless steel two-stage pusher centrifuge

Direct answer

For salt crystallization, screen-based continuous principles can be considered when representative crystals retain, drain and transport reliably; batch filtration can remain open when washing or batch control dominates. A decanter or another route may need review when fine solids, settling behaviour or process variability changes the separation mechanism. Do not make one principle universal.

What material and process boundary must be identified?

State the salt identity, hydrate or crystal form where relevant, production route, mother-liquor composition, impurities, temperature history and any recycle. “Salt slurry” is not a complete material definition.

Do not transfer a result from another grade, plant or supplier without checking that feed preparation, liquid phase, particle behaviour and measurement method match.

What feed data change the decision?

salt crystal separation feed review
Variable Buyer input Selection effect
Crystal distribution Representative distribution, fines tail, shape and fragility Screen retention, drainage, transport and breakage review
Mother liquor Composition, density, viscosity, temperature and corrosion contributors Materials, drainage, washing and containment
Feed solids Minimum, normal and maximum with variability Cake stability, throughput basis and control
Wash duty Liquid, sequence, ratio, purity target and recovery route Principle, residence and test plan

Which centrifuge principles should be screened?

The rows below are routing questions, not universal recommendations. A qualified review can keep more than one principle open until representative behaviour and project priorities are understood.

Initial principle screen
Principle Review when Do not assume
Pusher Free-draining crystals form a stable screen-retained cake and continuous transport is credible. Do not infer fit from salt name.
Screen scroll Screen retention and scroll transport can be demonstrated. Do not ignore fines bypass or wear.
Peeler / basket Batch cake formation, washing or handling is preferred. Do not ignore heel, discharge or cycle time.
Decanter Settling and fine-solids behaviour point away from screen filtration. Do not assume the same cake or wash behaviour.

When is a pusher route credible?

A pusher route is credible only after the actual crystal distribution, free-draining tendency, cake stability, wash requirement and breakage response support continuous screen filtration.

Screen retention, stable cake formation, continuous transport and acceptable breakage should be demonstrated. A familiar chemical name does not establish those conditions.

When is a decanter route credible?

A decanter may be screened when fines, suspended solids or failure to retain on a screen make sedimentation more relevant, but the required product form and purity route must remain feasible.

Settling response, density difference, rheology, centrate target and screw transport should be reviewed together. Fine solids alone do not guarantee a successful decanter duty.

What should a representative material test record?

  • Sample identity, production source, collection date, storage and conditioning
  • Feed composition, solids, temperature, particle or settling observations and variability
  • Test apparatus, operating sequence, settings and any conditioning aid
  • Record screen retention, drainage, cake formation, transport response, fines loss and crystal change.
  • If washing is required, record wash distribution, recovery route and analytical result.
  • Mass-balance boundary, sample locations, analytical methods, raw results and observations
  • Limits of scale-up and open questions for engineering review

How should required results be written?

Performance terms need both a target and a test boundary
Result Required boundary
Cake moisture or dry solids Sampling point, method, feed envelope, stable-operation period and averaging
Solids recovery Mass-balance boundary, sampling period and analysis method
Filtrate or centrate quality Sampling location, solids method and conditioning basis
Purity or wash result Wash liquid, sequence, ratio and product analysis method
Allowable breakage Before/after sampling and agreed particle method
Throughput Solids or slurry basis, composition, temperature and operating range

Which materials and corrosion inputs are required?

Provide every liquor constituent and credible concentration range, including chlorides or other corrosion contributors, with temperature and cleaning exposures.

Preferred wetted material is a buyer input, not proof of compatibility. Ask the selected source to identify exact component scope, material evidence, fabrication limits, cleaning exposure and exclusions.

Blue and stainless steel two-stage pusher centrifuge

Material selection guide

Build a chemistry, temperature, cleaning and evidence matrix.

What safety and containment questions must be closed?

Provide the current SDS and identify dust, hot liquor, chemical exposure, pressure, vapor or area-classification concerns. Safety controls are project-specific.

If flammable solvent or combustible hazard is present, provide solvent identity, flash point, vapor data, area classification, inerting requirement and the buyer-requested standard. XiangtanExport does not state that a source is ATEX or IECEx compliant without scoped evidence.

What process interfaces belong in the RFQ?

  • Upstream vessel, crystallizer, reactor, thickener, pump or conditioning step
  • Minimum, normal and maximum feed and credible upset conditions
  • Downstream solids handling, dryer, dissolution, product recovery or disposal
  • Liquid recovery, recycle, treatment or solvent-recovery route
  • Control signals, interlocks, utilities, layout, lifting and maintenance access
  • Responsibility for piping, cabling, foundation, installation and commissioning

Which supplier questions prevent scope gaps?

  • Which submitted feed data and test evidence support the proposed principle?
  • What assumptions, exclusions and missing variables remain?
  • Which wetted materials apply to each component and what evidence is offered?
  • How are cake, recovery, liquid quality, washing and throughput results measured?
  • Which process results can be demonstrated at material-test, FAT and SAT stages?
  • What drawings, manuals, certificates, spares and commissioning inputs are included?
  • Which deviations from the controlled RFQ require buyer approval?

How should material test, FAT and SAT be separated?

Material testing examines separation behaviour. FAT verifies the agreed factory mechanical, control, safety and document scope. SAT verifies site integration and, when contracted, project performance under a stated feed and utility basis. Do not use a no-load FAT as evidence of cake moisture, recovery or throughput.

Blue hydraulic pusher centrifuge with stainless steel process housing

Material test, FAT and SAT guide

Assign conditions, witnesses, records, criteria and remedies.

Which documents should be in the contract?

  • Approved process and equipment data sheet
  • General arrangement, interface and foundation information
  • Wetted-material schedule and requested source evidence
  • Motor, controls, instruments, interlocks and utility list
  • Inspection and test plan, FAT/SAT protocols and records where included
  • Operation, safety, cleaning and maintenance manuals
  • Wear and spare-parts list
  • Packing, preservation, lifting and shipment documents
  • Buyer-required conformity evidence: availability subject to source confirmation

What should the technical RFQ include?

Attach the crystallizer or upstream description, mother-liquor data, particle report, production range, purity and moisture methods, washing plan and downstream dryer or handling interface.

Unknown values may be marked unknown. Keeping an explicit gap is safer than inserting a catalogue assumption that later becomes a contract conflict.

Submit the centrifuge technical RFQ

Preserve process, result, site, document and attachment inputs in one inquiry.

Related principles and buyer guides

Blue and stainless steel two-stage pusher centrifuge

Pusher centrifuge

Continuous filtering decision framework.

Blue hydraulic pusher centrifuge with stainless steel process housing

Screen scroll centrifuge

Continuous screen and scroll transport route.

Blue and stainless steel two-stage pusher centrifuge

Salt pusher selection guide

Build the detailed test and acceptance basis.

Commercial sourcing and export support

Product Sourcing

Structure the equipment requirement and evidence request.

Supplier Verification & Matching

Check source identity and capability privately.

Production & Order Follow-Up

Track design, materials, tests and release milestones.

Logistics & Shipping

Coordinate packing data and shipment interfaces.

Sources & references

GB 19815-2021, Centrifuge—Safety requirements, National Public Service Platform for Standards, published 2021-04-30, effective 2022-05-01, accessed 2026-09-07.

GB/T 10895-2025, Centrifuge & separator—Measurement and evaluation of mechanical vibration, National Public Service Platform for Standards, published 2025-08-01, effective 2026-02-01, accessed 2026-09-07.

Public sources establish standards context only. Supplier identity, model, performance, materials, certification evidence and commercial terms remain private and source-specific.

Frequently asked questions

Does this page select a machine for every salt crystal separation project?

No. It identifies data and tests needed for a project-specific engineering review.

Can two plants using the same material need different principles?

Yes. Feed preparation, particle behaviour, liquid properties, variability, washing and required results can differ.

Can a supplier catalogue value be used as a guarantee?

Not without an agreed feed envelope, measurement method, conditions and source commitment.

Are ATEX, IECEx or CE included automatically?

No. Required standards are buyer inputs; source-specific availability, scope and evidence require confirmation.

When is a material test useful?

When feed behaviour or scale-up assumptions materially affect principle, design or performance risk.

Does XiangtanExport reveal the supplier pool?

No. Candidate sources and scorecards stay private unless disclosure is approved for the transaction.

Send process data for technical review

Provide the material, feed envelope, separation target, utilities, site and document requirements. We will identify missing data before private supplier matching.

Review and evidence note

Last reviewed: 2026-09-07

This application page provides non-numeric selection logic. It does not confirm a supplier, machine size, performance guarantee, material compatibility or certification.

Final product availability, specification, documentation and commercial terms are confirmed during supplier matching and quotation.